| Location/Owner |
Contractor |
Start Date |
Duration |
Manpower |
Schedule |
Scope |
| SABIC |
BMWC |
ONGOING MAINTENANCE |
ONGOING |
5 |
40 HRS |
MAINTENANCE |
| MADISON |
ENERFAB |
ONGOING MAINTENANCE |
ONGOING |
10 |
4-10’s |
PLANTWIDE |
| ROCKPORT |
ENERFAB |
ONGOING MAINTENANCE |
ONGOING |
4 |
5-8’S |
PLANTWIDE |
| WARRICK/AGC |
STERLING |
ONGOING MAINTENANCE |
ONGOING |
4 |
VARIOUS |
PLANTWIDE |
| GPC |
SKANSKA |
ONGOING |
6 MONTHS |
6 |
40 HOURS |
INSTALL NEW EQUIPMENT |
| GIBSON-FALL ’22 |
STERLING INDUSTRIAL |
UNIT2 AUGUST 28, UNIT 1 OCT 6 |
10 WEEKS EACH |
140 PER UNIT |
|
MAJOR BOILER OUTAGES |
| GIBSON-FALL ’22 |
BOWEN |
EARLY SEPT |
16 WEEKS? |
15 PLUS |
6-10’S |
AIR HEATERS |
| ROCKPORT FALL ’22 |
ENERFAB |
SEPT 10 |
10 WEEKS |
40 PLUS |
TBD |
TBD |
| CULLEY FALL ’22 |
STERLING |
AUGUST 1 |
12 WEEKS |
25 PLUS |
6-10’S |
BOILER |
| CULLEY FALL ’22 |
ICS |
OCT 1 |
6-8 WEEKS |
TBD |
6-10’S |
DUCTWORK |
| MADISON FALL ’22 |
ENERFAB, ERSHIGS |
SEPT 10-NOV 14TH |
TBD |
TBD |
TBD |
|
| SABIC FALL ’22 |
BMWC |
OCT. 5 |
4 WEEKS |
15 MORE |
6-10’S |
|
| RIVERVIEW ENERGY / DALE |
CONTRACTOR BID DOCUMENTS NOT RELEASED YET |
PEC REPORT NOW SAYS BREAK GROUND MAY 2023 |
34 MONTHS START TO FINISH |
TBD |
TBD |
COAL TO DIESEL PLANT CONSTRUCTION |
| MIDWEST FERTILIZER IN POSEY COUNTY |
CONTRACTOR BID DOCUMENTS NOT RELEASED YET |
MOVING FORWARD WITH DESIGN AND FINANCING |
2-3 YEARS |
TBD |
TBD |
FERTILIZER PLANT |