Zone: 1 Date: MAY 23, 2023
Location/ Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
---|
CLIFFS BURNS HARBOR #1 HOOD | OUT FOR BID | JUNE 5 | 15 DAYS | 12-16 BM | 7-10 2 SHIFTS | HOOD PANELS, HEADERS,ETC. |
US STEEL Q-BOP | AIS | JUNE 12 | 3 WEEKS | 5-7 BM PER SHIFT | 7-10’S 2 SHIFTS | CONE CHANGE, HOOD WORK |
US STEEL #14 BF | AIS
MORRISON
SONGER | JULY10 | 8 DAYS | 30-40 BM | 7-12’S 2-SHIFTS | FURNACE SHELL, GAS SYSTEM, ETC. |
US STEEL Q-BOP | AIS | JULY 10 | 5 DAYS | 20 BM | 5-12’S 2-SHIFTS | STEEL SHOP OUTAGE |
BP WHITING | NOOTER | EARLY OR MID SEPTEMBER | 6-8 | 10-12 BM | 6-10’S
2-SHIFTS | HEATERS |
CLIFFS EAST 4SP 60 HOOD | STEVENS ENG. | SEPTEMBER??
WAITING ON DELIVERY | 3 WEEKS | TBD | 7-10 2 SHIFTS | HOOD REPLACEMENT |
US STEEL 63 STOVE | TBD | Fall as of now | TBD | TBD | TBD | TBD |