Zone: 3 Date: JUNE 14, 2024
Location | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
PETERSBURG | | | | | | POSSIBLE OUTAGE IN OCTOBER |
CULLEY | | | | | | NO SCHEDULED OUTAGES FOR 2024 |
ABBROWN GAS | STERLING | ONGOING | LONG | CURRENTLY FULL | 5-9’S | BUILDING SIMPLE CYCLE GAS UNITS |
SABIC 2024 | BMWC, NOOTER, ENERFAB, TURNER | MID TO LATE JULY | 3 MONTHS | APPROXIMATELY 200 PLUS AT PEAK? | VARIOUS | PER BMW, ALTEM 90 DAY OUTAGE STARTING AFTER JULY 27, PETCHEM-AUG 26-OCT 25. |
Gibson 2024 | STERLING | ONGOING | 4 weeks | Around 100 PER SHIFT | 7-10’s | Boiler and dampers |
AEP ROCKPORT | ENERFAB | | | | | NO MORE OUTAGES SCHEDULED |
Evansville riverfront near Mulzers | Sterling | ONGOING | TILL NOVEMBER. POSS GETTING MORE WORK TILL NEXT SUMMER FOR ANOTHER 30-40 MEN | 8 TOTAL | 5-10’S | Sterling will fabricate stacks for Kiewit for combined cycle gas turbines at TVA plants |
CLIFTY CREEK | ENERFAB | FALL OUTAGE | TBD | TBD | TBD | TBD |