Zone: 2 Date: September 6, 2022
Location/Owner Contractor Start Date Duration Manpower Schedule Scope
TATE & LYLE KENNEDY TANK ONGOING ONGOING 11 5/10s MAINTENANCE
VERTELLUS KENNEDY TANK ONGOING ONGOING 6 40 HOURS MAINTENANCE
Vertellus Kennedy Tank ONGOING 4-5 weeks 12 6/12s OUTAGE
MEROM STERLING ONGOING ONGOING 1 40 MAINTENANCE
SG SOLUTIONS TBD Still passing legislation CO2 NEW 50 MIL $ INVESTOR 3-4 YEAR STATING 2022 START TBD TBD FERTILIZER &HYDROGEN PLANT
MEROM STERLING OCTOBER 3 weeks 10-20 5/10s OUTAGE
SUGAR CREEK FREITAG SEPTEMBER 6th 2 WEEKS 5-6 6/10s TUBE WORK HRSG