Zone: | 2 | Date: | September 6, 2022 |
Location/Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
TATE & LYLE | KENNEDY TANK | ONGOING | ONGOING | 11 | 5/10s | MAINTENANCE |
VERTELLUS | KENNEDY TANK | ONGOING | ONGOING | 6 | 40 HOURS | MAINTENANCE |
Vertellus | Kennedy Tank | ONGOING | 4-5 weeks | 12 | 6/12s | OUTAGE |
MEROM | STERLING | ONGOING | ONGOING | 1 | 40 | MAINTENANCE |
SG SOLUTIONS | TBD | Still passing legislation CO2 NEW 50 MIL $ INVESTOR | 3-4 YEAR STATING 2022 START | TBD | TBD | FERTILIZER &HYDROGEN PLANT |