Zone: 1 Date: September 6th , 2022
Location/Owner Contractor Start Date Duration Manpower Schedule Scope
BP WHITING                 4UF D5 REACTOR NOOTER ONGOING 6-8 WEEKS 4 PER SHIFT 6-10S                 2 SHIFTS INCONEL & STAINLESS WELDERS
CLIFFS BURNS HARBOR #1 HOOD MORRISON SEPT.

EXACT DATE TBD

11 DAYS TBD 7-12’S 2 SHIFTS HOOD OUTAGE
CLIFFS BURNS HARBOR #2 HOOD MORRISON AFTER #1 HOOD 21 DAYS  TBD 7-12’S 2 SHIFTS HOOD OUTAGE
CLIFFS BURNS HARBOR MORRISON OCTOBER \21 DAYS TBD 7-10’S FANS, DUCT,

CHUTES

CLIFFS BH                    SINTER PLANT TBD AUGUST 8 3 WEEKS TBD TBD DUCT WORK, FANS, ETC
NIPSCO  MICHIGAN CITY UNIT 12 BMWC SEPT 12TH 8-9 WEEKS TBD SCOPE CHANGE IN PROGRESS  6-10s                 2 SHIFTS TBD
BP WHITING                     CAT CRACKER NOOTER SEPT. 15TH 7-8 WEEKS 100 BM 6-10s                  2 SHIFTS DRUMS, EXCHANGERS, ETC.
BP WHITING                    SCR TAR BMWC SEPT. 9 6-7 WEEKS 45 BM 6-10S                  2 SHIFTS EXCHANGERS, ETC.
CLIFFS BH                    #7 BOILER BMWC 2023 8-10 WEEKS 50 BM 6-10S                2 SHIFTS RETUBE