Zone: | 1 | Date: | September 6th , 2022 |
Location/Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope |
BP WHITING 4UF D5 REACTOR | NOOTER | ONGOING | 6-8 WEEKS | 4 PER SHIFT | 6-10S 2 SHIFTS | INCONEL & STAINLESS WELDERS |
CLIFFS BURNS HARBOR #1 HOOD | MORRISON | SEPT.
EXACT DATE TBD |
11 DAYS | TBD | 7-12’S 2 SHIFTS | HOOD OUTAGE |
CLIFFS BURNS HARBOR #2 HOOD | MORRISON | AFTER #1 HOOD | 21 DAYS | TBD | 7-12’S 2 SHIFTS | HOOD OUTAGE |
CLIFFS BURNS HARBOR | MORRISON | OCTOBER | \21 DAYS | TBD | 7-10’S | FANS, DUCT,
CHUTES |
CLIFFS BH SINTER PLANT | TBD | AUGUST 8 | 3 WEEKS | TBD | TBD | DUCT WORK, FANS, ETC |
NIPSCO MICHIGAN CITY UNIT 12 | BMWC | SEPT 12TH | 8-9 WEEKS | TBD SCOPE CHANGE IN PROGRESS | 6-10s 2 SHIFTS | TBD |
BP WHITING CAT CRACKER | NOOTER | SEPT. 15TH | 7-8 WEEKS | 100 BM | 6-10s 2 SHIFTS | DRUMS, EXCHANGERS, ETC. |
BP WHITING SCR TAR | BMWC | SEPT. 9 | 6-7 WEEKS | 45 BM | 6-10S 2 SHIFTS | EXCHANGERS, ETC. |
CLIFFS BH #7 BOILER | BMWC | 2023 | 8-10 WEEKS | 50 BM | 6-10S 2 SHIFTS | RETUBE |