Zone: 3 Date: January 9, 2026
| Location | Contractor | Start Date | Duration | Manpower | Schedule | Scope | MORE FUND USED |
| UPCOMING WORK: | | | | | | | |
| PETERSBRG | B&W | U3 Outage: February 2nd – May 10th
U4 Outage: June 29th – November 1st
U4 Commissioning/Demobilization: November 2nd – December 13th | 1 YEAR | OVER 200 AT PEAK
CURRENTLY 47 ON SITE | 5 10S NOW, START 6-10’S FEBRUARY | GAS CONVERSION | NO |
| ROCKPORT | ENERFAB | EARLY MARCH? | TBD | TBD | TBD | SCR CATALYST CHANGE, CASING LEAKS, EGG CRATES | NO |
| DUKE ENERGY GIBSON STATION | STERLING | EARLY MARCH? | TBD | TBD | TBD | T&M | NO |
| CLIFTY CREEK | ENERFAB | SPRING OUTAGE | TBD | TBD | TBD | TBD | NO |
| AEP ROCKPORT GAS TURBINES | BIDDING | MOBILIZE SPRING 2027 | TBD | 150 AT PEAK | TBD | 4 COMBINED CYCLE GAS TURBINES | NO |
| ABBROWN COMBINED CYCLE GAS TURBINE | BIDDING | BREAK GROUND 3RD QUARTER 2026 | 3 YEARS TOTAL | 150 AT PEAK | TBD | 1 COMBINED CYCLE | NO |