Zone: 3 Date: NOVEMBER 20, 2025
| Location | Contractor | Start Date | Duration | Manpower | Schedule | Scope | MORE FUND USED |
| UPCOMING WORK: | | | | | | | |
| ROCKPORT | ENERFAB | OCT 25 | ONGOING. 2-3 WEEKS LEFT | 40 | 6-10’S | PRECIP EGG CRATES, EXP JOINTS, CASING LEAKS | NO |
| PETERSBRG | B&W | Mobilization/U3 Pre-Outage: September 30th (or sooner) – February 1st
U3 Outage: February 2nd – May 10th
U3 Commissioning/U4 Pre-Outage: May 11th – June 28th
U4 Outage: June 29th – November 1st
U4 Commissioning/Demobilization: November 2nd – December 13th | 1 YEAR | OVER 200 AT PEAK
CURRENTLY 28 ON SITE | WAS TOLD 6-10’S | GAS CONVERSION | NO |
| AEP ROCKPORT GAS TURBINES | BIDDING | MOBILIZE SPRING 2027 | TBD | 32 PEAK | TBD | BUILD 2 SIMPLE CYCLE GAS TURBINES TO START, MORE TO FOLLOW. | NO |