Zone: 1 Date: Nov 21st, 2025
| Location/ Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope | MORE Fund
Y / N |
|---|
| Cliffs Burns Harbor #3 Hood | Morrison | Dec 7th | 5-6 Days | 8 Per shift | 2 Shifts 12hrs | Maintenance Repairs | N |
Us Steel
| AIS | Dec 1st | 3 weeks | 5-7 on night shift | 6-10s | Maintenance Repairs | N |
US Steel
14 Furnace | Morrison and Songer | June 2026 | 90 days | TBD | 2 shifts | Rebuild | N |
| Nipsco Wheatfield | Possibly BOLT | 2026 Doing ground work now | 10-12 months | peak 25 BM | TBD 5-10s possibly | 2-4 New Peaking Units | N |