Zone: 1 Date: April 10th, 2025
Location/ Owner | Contractor | Start Date | Duration | Manpower | Schedule | Scope | MORE Fund
Y / N |
---|
Ozinga / By Old Inland Electric Furnace | Morrison | late April | 6 Months | 3-5 Boilermakers at first.
Peek will be 20-25 Guys | 1 shift 40hrs | Duct stacks | N |
Cleveland Cliffs West #6 Boiler | Morrison | End of April Waiting on tubes | 2 weeks | 5-6 Boilermakers | 1 shifts 6-10s | Maintenance Outage | N |
Nipsco Unit 12 | BMWC | May 5th | 4 Weeks | 12-16 Boilermakers | 1 shift 6-10s | Boiler Maintenance | N |
Nipsco Unit 17 & 18 | See Note at end or report | | | | | | N |
BP Whiting
#12 Pipe Still | Nooter | April 23rd | 6 weeks | 10-15 per shift | 2 shifts 6-10s | Heater tubes | N |
BP Whiting
Waste Water Stripping Project | BMWC | Mid June Early July | 6-8 Weeks | 10-12 Boilermakers | 1 Shift
6-10’s | Vessels
Drums
Stacks Ductwork
Coolers | N |